Sample for site Instruction in construction

Sample for site Instruction

 

SITE INSTRUCTION SHEET

CONTRACT NAME: Routine Maintenance of .. Road (6.4km), Routine (20.16km) and Periodic Maintenance (5.0 km) and Construction of Culverts and Side Drains of  Urban Roads

 

CONTRACT NO: TRR/2020/2021/..

CONSULTANT: District Engineer (Works) –

CONTRACTOR: M/S ..... Co.Ltd P. O. Box ......, .

 

SITE INSTRUCTION NO:  01

DATE: 2nd  May, 2017

INSTRUCTION DETAILS

The client has decided to add more works to this contract

Therefore you are hereby instructed to carry out immediately the following additional works;

CONSTRUCTION OF CULVERTS AND SIDE DRAINS ALONG URBAN ROAD

1.       Reinforced concrete class 20 (1:2:4) access slab ( 22 nos ).

 

SIGNED:…………………………….   

                    

        District Works Engineer

                   

 

DATE:……………………………

 

 

SIGNED:……………………………

 

                        Contractor

 

 

 

DATE:…………………………….

 

 

 


Comments