SITE  REPORT

PROJECT NAME: CONSTRUCTION, COMPLETION AND PROVISION OF SCHOOL BUILDING FACILITIES

SITE: Name.

ACTIVITIES: CONSTRUCTION OF VIP PIT LATRINES (2 STANCES) STAFF, CONSTRUCTION OF VIP PIT LATRINES (8 STANCES) STUDENTS AND COMPLETION OF LABORATORY.

02/12/2016: WORK DONE

1.       Excavation of students pit latrines

2.       Blocks making 

03/12/2016: WORK DONE

1.       Construction of staffs soak pit

2.       Construction of staff latrine foundation

3.       Excavation of students pit latrine

4.       Blocks making

5.       Curing of  blocks

04/12/2016: WORK DONE

1.       Construction of staff soak pit

2.       Construction of super structure building of staff latrine

3.       Excavation of students  pit latrine

4.       Curing of blocks, foundations, and staff  soak pit

5.       Block making

05/12/2016: WORK DONE

1.       Blocks making

2.       Curing of blocks, wall of staff latrine and staff  soak pit

3.       Excavation of students  pit latrine

4.       Preparation of form work

06/12/2016: WORK DONE

1.       Pouring of concrete to the lintel of staff  latrine building

2.       Preparation of steel fixing to the slab of students  soak pit

3.       Block making

4.       Excavation of students pit latrine

5.       Curing of blocks, wall of staff latrine and staff  soak pit

6.       Collection of fine aggregate (sand) to the laboratory building

7.       Curing of blocks, wall of staff latrine and staff  soak pit

07/12/2016: WORK DONE

1.       Excavation of students pit latrine

2.       Curing of blocks, wall of staff latrine and staff  soak pit

3.       Laying hardcore to the laboratory  room

4.       Block making

08/12/2016: WORK DONE

1.       Excavation of students pit latrine

2.       Curing of blocks, wall of staff latrine and staff  soak pit

3.       Block making

 

09/12/2016: WORK DONE

1.       Site meeting

2.       Excavation of students pit latrine

3.       Curing of blocks, wall of staff latrine and staff  soak pit

4.       Block making

5.       Concrete footing to students pit latrine

10/12/2016: WORK DONE

1.       Curing of blocks, wall of staff latrine and staff  soak pit

2.       Block making

3.       Walling of students pit latrine

 

 

Prepared by;

………………………………

Name

Technician ,

 

……………………………..

Name

Technician

 

 

 